TL;DR
- Spain's Royal Decree 1032/2026, published on 21 November, makes data centres with 10 MW or more of grid access that are not yet connected cover 80% of their power with new renewables, matched hour by hour (BOE; MITECO).
- Projects that already hold grid permits have six months to comply or the permits lapse (BOE). Data centres hold 15 GW of granted grid access, with more than 20 GW waiting, the minister said (Euronews; Europa Press).
- On 23 November the industry body SpainDC said it would appeal to the Supreme Court on Wednesday or Thursday and seek a suspension (Europa Press).
Spain has turned its grid queue into a renewable power test. Under a decree in force since the weekend, a data centre that wants its place on the network must show that new renewable plants cover 80% of its power, hour by hour (MITECO). The rule lands on a pipeline that already holds 15 GW of granted access, and the industry is heading to court to stop it.
What does the decree require?
The Council of Ministers approved the decree on Friday 20 November (MITECO). It was published in the official gazette on Saturday 21 November and takes effect the day after publication (BOE).
It applies to data centres with grid access of 10 MW or more that were not connected when it took effect: new applications, pending ones and permits not yet connected (BOE).
Two tests sit at its core. The first is additionality: 80% of consumption must come from self-consumption or contracts with renewable plants that started no more than 36 months before the data centre opens; solar plants without an existing power purchase agreement count whatever their age (BOE). The second is hourly matching: at least 80% of power use must be backed by an equal volume of renewable electricity in the same hour (BOE).
There is a softer route for five years. Operators that accept being first in line for automatic power cuts need 60% renewable cover in peak hours until the end of 2028. From 2029 the bar is 70% in peak hours and 60% in the next band (BOE).
Only centres commissioned before the end of 2030 can use the softer route. Once the five years end, those centres must meet the full 80% hourly test (BOE). Breaches can suspend grid access and connection rights for up to three years (MITECO).
What happens to projects already in the queue?
This is where the decree reaches into land and development value. Projects with access and connection permits but no connection yet have six months to prove compliance. If they fail, the permits lapse and their guarantees are enforced (BOE). Applications still being processed have three months, after which they are refused (BOE).
| Position on 22 November | Deadline | If not met |
|---|---|---|
| Permits granted, not connected | Six months | Permits lapse, guarantees enforced |
| Application pending | Three months | Application refused |
| Application held for a grid tender | Three months | Application refused; system operator then decides on the node |
The stock at stake is large. Spain has granted data centres 15 GW of grid access, close to 40% of national peak demand, and more than 20 GW are in the queue (Europa Press; Euronews).
The industry's own forecast measures something else, IT capacity: in October, SpainDC said it expects that to rise nearly sixfold to 2.5 GW between 2025 and 2030, according to Bloomberg via Energy Connects.
Why does the government say it needs the rule?
Power prices. Minister for the Ecological Transition Sara Aagesen said that without the decree consumers would face a EUR 5,000m impact on their bills (MITECO). Euronews reported the figure as up to EUR 5,000m a year, EUR 4,000m from wholesale prices and EUR 1,000m from capacity mechanisms. In one scenario, industrial users would pay 25% more for electricity, she said, citing Ireland as the case to avoid (Cadena SER).
The industry disputes the numbers. A Wood Mackenzie study for SpainDC finds that 3 GW of data centre demand in 2030 would lift the average final power price by about 1.3% (ABC). SpainDC also says data centres use 0.8% of Spain's electricity, against 23% in Ireland (Europa Press).
Data centres' share of national electricity use, according to SpainDC (%)
The final text is softer than the August draft, after more than 600 submissions and a report from the competition authority CNMC (Europa Press).
What is the industry taking to the Supreme Court?
SpainDC said on 20 November that it would appeal and seek an interim suspension (Europa Press). At its annual congress in Madrid on Monday 23 November, it set the timing. SpainDC plans to file at the Supreme Court on Wednesday or Thursday, after President Emilio Díaz convenes the board to approve it (Europa Press). Expansión reported that Wednesday is the likely day.
The brief is already drafted with Uría Menéndez as legal adviser (El Periódico). Its grounds include the urgent procedure, encroachment on regional powers, technical impossibility and disproportionate fines (Expansión). SpainDC wants Amazon, Google and Microsoft to file their own appeals. The regional governments of Madrid & Aragón have confirmed they intend to go to the Supreme Court too (El Periódico).
The association puts EUR 9,000m of capital at risk, an estimate it has not yet updated (Europa Press). It says EUR 66,900m of planned investment to 2030 is threatened (El Periódico). The Supreme Court has no fixed deadline to rule on interim measures (Expansión).
Politics adds a second clock. Spain votes on 29 November, and the Partido Popular has said it would repeal the decree if it governs (Europa Press). A repeal would itself need reports from the CNMC & the Council of State and could take several months (Expansión).
Why it matters
Our view: if the Supreme Court grants the interim suspension, then holders of unconnected permits within the 15 GW of granted access keep building on the old terms while the case runs. If it refuses, then each of them has six months to tie new renewable plants to its site, and permits without that power lose value.
If the rule stands, then a new data centre site in Spain is priced as a power package: land, grid access and contracts with renewable plants no more than 36 months old. If a new government repeals it, then the several months a repeal takes still run against the transitional deadlines.