Data Centres Evolving story · updated 24 Nov 2026, 15:00 CET

Spain ties data centre grid access to hourly renewable power

A new royal decree makes every new data centre of 10 MW or more prove that new renewables cover 80% of its power, matched hour by hour, or lose its place on the grid. The industry says it will ask the Supreme Court to freeze the rule this week.

Call for Experts: Hourly matching Court & suspension Capital & pricing

10 min Read time
24 Nov Published
Article graphic on Spanish data centres: Spain ties data centre grid access to hourly renewable power

TL;DR

  • Spain's Royal Decree 1032/2026, published on 21 November, makes data centres with 10 MW or more of grid access that are not yet connected cover 80% of their power with new renewables, matched hour by hour (BOE; MITECO).
  • Projects that already hold grid permits have six months to comply or the permits lapse (BOE). Data centres hold 15 GW of granted grid access, with more than 20 GW waiting, the minister said (Euronews; Europa Press).
  • On 23 November the industry body SpainDC said it would appeal to the Supreme Court on Wednesday or Thursday and seek a suspension (Europa Press).

Spain has turned its grid queue into a renewable power test. Under a decree in force since the weekend, a data centre that wants its place on the network must show that new renewable plants cover 80% of its power, hour by hour (MITECO). The rule lands on a pipeline that already holds 15 GW of granted access, and the industry is heading to court to stop it.

What does the decree require?

The Council of Ministers approved the decree on Friday 20 November (MITECO). It was published in the official gazette on Saturday 21 November and takes effect the day after publication (BOE).

It applies to data centres with grid access of 10 MW or more that were not connected when it took effect: new applications, pending ones and permits not yet connected (BOE).

Two tests sit at its core. The first is additionality: 80% of consumption must come from self-consumption or contracts with renewable plants that started no more than 36 months before the data centre opens; solar plants without an existing power purchase agreement count whatever their age (BOE). The second is hourly matching: at least 80% of power use must be backed by an equal volume of renewable electricity in the same hour (BOE).

There is a softer route for five years. Operators that accept being first in line for automatic power cuts need 60% renewable cover in peak hours until the end of 2028. From 2029 the bar is 70% in peak hours and 60% in the next band (BOE).

Only centres commissioned before the end of 2030 can use the softer route. Once the five years end, those centres must meet the full 80% hourly test (BOE). Breaches can suspend grid access and connection rights for up to three years (MITECO).

What happens to projects already in the queue?

This is where the decree reaches into land and development value. Projects with access and connection permits but no connection yet have six months to prove compliance. If they fail, the permits lapse and their guarantees are enforced (BOE). Applications still being processed have three months, after which they are refused (BOE).

Position on 22 NovemberDeadlineIf not met
Permits granted, not connectedSix monthsPermits lapse, guarantees enforced
Application pendingThree monthsApplication refused
Application held for a grid tenderThree monthsApplication refused; system operator then decides on the node

The stock at stake is large. Spain has granted data centres 15 GW of grid access, close to 40% of national peak demand, and more than 20 GW are in the queue (Europa Press; Euronews).

The industry's own forecast measures something else, IT capacity: in October, SpainDC said it expects that to rise nearly sixfold to 2.5 GW between 2025 and 2030, according to Bloomberg via Energy Connects.

Why does the government say it needs the rule?

Power prices. Minister for the Ecological Transition Sara Aagesen said that without the decree consumers would face a EUR 5,000m impact on their bills (MITECO). Euronews reported the figure as up to EUR 5,000m a year, EUR 4,000m from wholesale prices and EUR 1,000m from capacity mechanisms. In one scenario, industrial users would pay 25% more for electricity, she said, citing Ireland as the case to avoid (Cadena SER).

The industry disputes the numbers. A Wood Mackenzie study for SpainDC finds that 3 GW of data centre demand in 2030 would lift the average final power price by about 1.3% (ABC). SpainDC also says data centres use 0.8% of Spain's electricity, against 23% in Ireland (Europa Press).

Data centres' share of national electricity use, according to SpainDC (%)

  • Ireland23%
  • Netherlands5%
  • Spain0.8%
Figures from SpainDC's statement of 20 November 2026, as reported by Europa Press.Source: Europa Press

The final text is softer than the August draft, after more than 600 submissions and a report from the competition authority CNMC (Europa Press).

What is the industry taking to the Supreme Court?

SpainDC said on 20 November that it would appeal and seek an interim suspension (Europa Press). At its annual congress in Madrid on Monday 23 November, it set the timing. SpainDC plans to file at the Supreme Court on Wednesday or Thursday, after President Emilio Díaz convenes the board to approve it (Europa Press). Expansión reported that Wednesday is the likely day.

The brief is already drafted with Uría Menéndez as legal adviser (El Periódico). Its grounds include the urgent procedure, encroachment on regional powers, technical impossibility and disproportionate fines (Expansión). SpainDC wants Amazon, Google and Microsoft to file their own appeals. The regional governments of Madrid & Aragón have confirmed they intend to go to the Supreme Court too (El Periódico).

The association puts EUR 9,000m of capital at risk, an estimate it has not yet updated (Europa Press). It says EUR 66,900m of planned investment to 2030 is threatened (El Periódico). The Supreme Court has no fixed deadline to rule on interim measures (Expansión).

Politics adds a second clock. Spain votes on 29 November, and the Partido Popular has said it would repeal the decree if it governs (Europa Press). A repeal would itself need reports from the CNMC & the Council of State and could take several months (Expansión).

Why it matters

Our view: if the Supreme Court grants the interim suspension, then holders of unconnected permits within the 15 GW of granted access keep building on the old terms while the case runs. If it refuses, then each of them has six months to tie new renewable plants to its site, and permits without that power lose value.

If the rule stands, then a new data centre site in Spain is priced as a power package: land, grid access and contracts with renewable plants no more than 36 months old. If a new government repeals it, then the several months a repeal takes still run against the transitional deadlines.

Call for experts.

Hourly matching

Data centre operators and developers, Spain & Southern Europe

Spain's Royal Decree 1032/2026 makes data centres of 10 MW or more cover 80% of their power with new renewables, matched hour by hour. Projects with grid permits that are not yet connected have six months to comply or the permits lapse. SpainDC argues the hourly test is technically impossible, according to Expansión.

Your view

Is the hourly test impossible? SpainDC argues the hourly test is technically impossible to meet. Do you agree, or does your experience suggest otherwise?

Your example

What does compliance cost? What would it take your sites to match 80% hour by hour? Please share a cost or an example.

Answer by email

Share

Court & suspension

Energy and infrastructure lawyers, Spain

SpainDC says it will appeal the decree to the Supreme Court this week and ask for an interim suspension. Expansión reports the court has no fixed deadline to rule on interim measures.

Your view

Will the court suspend the decree? One question from our analysis: is an interim suspension of the decree realistic? Do you agree, or not?

Your example

What should permit holders do meanwhile? What should a permit holder do while the court decides on suspension? Please share an example.

Answer by email

Share

Capital & pricing

Data centre and digital infrastructure investors, Europe

SpainDC puts EUR 9,000m of capital at risk and says EUR 66,900m of planned investment to 2030 is threatened. Spain votes on 29 November, and the Partido Popular has said it would repeal the decree.

Your view

Are sites priced by power first? Our analysis suggests investors will now price Spanish sites by their power contracts first. Agree, or not?

Your example

Does capital move elsewhere? Would you move a planned Spanish project to another country now? Please share an anonymised example.

Answer by email

Share

FAQ

Which data centres does the decree cover?

Those with grid access of 10 MW or more that were not connected when it took effect: new applications, pending ones and permits not yet connected (BOE).

What does hourly matching mean?

In every hour, at least 80% of the power a data centre uses must be backed by the same volume of renewable electricity (BOE).

Has the appeal been filed?

SpainDC said on 23 November that it would file on Wednesday or Thursday this week, after a board vote (Europa Press).

Who else is challenging the decree?

The regional governments of Madrid & Aragón have confirmed they intend to go to the Supreme Court (El Periódico).

Sources (10)